Ontario’s Construction Act controls several important payment and dispute rules for construction projects in the province. It covers construction liens, mandatory holdbacks, prompt payment, statutory trusts, and interim adjudication. Major amendments took effect on January 1, 2026, so older explanations can now be misleading.
Quick answer: Ontario’s construction legislation protects payment rights throughout a project’s contractual chain. It generally requires a 10% holdback, sets prompt-payment deadlines, creates lien rights, and permits rapid adjudication of qualifying disputes. Since January 1, 2026, new rules also govern annual holdback releases, invoice deficiencies, and adjudication procedures.
| Key rule | Ontario position in 2026 |
|---|---|
| Main legislation | Construction Act, R.S.O. 1990, c. C.30 |
| Basic holdback | Generally 10% of supplied services or materials |
| Owner payment deadline | Generally 28 days after receiving a proper invoice |
| Invoice deficiency notice | Generally within 7 days of receiving the invoice |
| Typical lien preservation period | 60 days after the applicable triggering event |
| Perfection after preservation | Generally within the following 90-day period |
| Annual holdback release | Mandatory under the 2026 regime |
| Adjudication | Available for prescribed construction disputes |
| Province covered | Ontario |
Key Takeaways
- Canada does not have one nationwide statute bearing this name for every construction project.
- Ontario’s legislation creates lien, trust, payment, holdback, and adjudication rights.
- A basic statutory holdback generally equals 10% of supplied services or materials.
- Prompt-payment obligations can begin when a contractor submits a proper invoice.
- Owners now have seven days to identify qualifying invoice deficiencies in writing.
- Ontario introduced mandatory annual holdback releases from January 1, 2026.
- Construction lien deadlines can expire quickly and depend on specific triggering events.
- Federal projects may instead involve Canada’s Federal Prompt Payment for Construction Work Act.
What the Construction Act Does in Ontario
The Construction Act is an Ontario statute rather than a general Canadian construction code. It regulates important financial relationships among owners, contractors, subcontractors, suppliers, and other construction participants. The legislation also provides remedies that operate alongside ordinary contractual rights. Its payment framework has several connected parts. These include statutory trusts, prompt payment, construction liens, holdbacks, and interim adjudication. Each mechanism addresses a different risk created when money moves through a construction project.
That distinction matters because unpaid invoices are not always ordinary debt claims. A contractor or supplier may have statutory rights unavailable in a normal commercial dispute. Missing a statutory deadline can also remove a remedy even while a contractual claim remains. The current consolidated statute on e-Laws is the authoritative text.
Is There One Construction Law for All of Canada?
Canada does not use one provincial construction statute for every private project nationwide. Provinces generally establish their own lien, payment, and construction-remedy systems. Federal legislation can apply to qualifying work involving federal real property or federal immovables. The Federal Prompt Payment for Construction Work Act has been in force since December 9, 2023. It creates payment and adjudication rules for construction work within its federal scope. The legislation also permits provinces with sufficiently similar systems to be designated under the federal framework.
For that reason, a Canadian construction dispute should start with jurisdiction. Identify the project location, property owner, contract structure, and whether federal property is involved. A deadline drawn from another province may offer no protection in Ontario.
Prompt Payment Rules: How the Payment Clock Works
Ontario’s prompt-payment system is designed to move money through the construction chain on set timelines. An owner generally must pay a contractor within 28 days after receiving a proper invoice. Payment obligations farther down the chain can then arise within shorter periods. The legislation also permits non-payment in specified circumstances when proper notice requirements are met. Parties cannot safely treat silence or an informal complaint as a substitute for statutory notice. Contract administrators therefore need reliable systems for reviewing invoices and recording deadlines.
For an ordinary unpaid debt outside the statutory construction framework, different procedures may apply. Lawverra’s Small Claims Court Ontario guide explains Ontario’s separate process for lower-value civil claims. Construction claims need separate analysis because lien and adjudication rights can change the available route.
Proper Invoices and the New Seven-Day Rule
A proper invoice must contain information required by the statute and applicable contract terms. Required details can include the contractor, billing period, contractual authority, work supplied, amount payable, and payment information. The 2026 amendments also changed how invoice deficiencies are treated. Since January 1, 2026, a deficient invoice can be deemed proper unless the owner responds promptly. The owner generally has seven days after receipt to give written notice identifying the deficiency. That notice must also explain what is required to correct the problem.
This change makes invoice administration more time-sensitive for owners. Letting a questionable invoice sit unanswered can have consequences under the payment regime. Contractors should likewise retain evidence showing exactly when an invoice was delivered.
Construction Liens and the 60-Day Deadline
Ontario law gives qualifying suppliers of services or materials a lien connected with the improvement. The right arises when eligible services or materials are first supplied. Its preservation period does not run forever and depends on statutory triggering events. For many claims, the relevant preservation period is 60 days. The precise starting point varies according to the claimant’s position and project events. Completion, abandonment, termination, last supply, and publication of substantial performance can all matter.
Preserving a lien is also not the final enforcement step. A preserved lien generally expires unless perfected within the following 90-day statutory period. Perfection normally requires starting the enforcement action and taking any required registration step. Anyone considering ordinary litigation should distinguish these deadlines from normal civil limitation periods. Lawverra’s Ontario Rules of Civil Procedure guide explains the broader court framework. Construction lien proceedings remain subject to their own statutory requirements.
How the 10% Holdback Works
The statute generally requires a payer to retain 10% of the price of supplied services or materials. This basic holdback supports lien rights arising farther down the contractual chain. It applies whether the agreement provides progress payments or payment at completion. A separate finishing-work holdback can also apply after substantial performance. The amount relates to services or materials still required to complete the contract. The statutory rules determine when these retained amounts can be released.
The holdback should not be confused with an ordinary contractual security deposit. It is part of Ontario’s statutory lien framework. Payment and release must therefore be considered alongside outstanding lien rights.
The Major 2026 Change: Mandatory Annual Holdback Release
One of the most significant 2026 reforms concerns annual release of accrued holdback. Following each contract anniversary, an owner must address the annual release process required by section 26. The owner must publish the prescribed notice within 14 days after that anniversary. The new regime is particularly important for long-running projects. Previously, annual or phased release depended much more heavily on the applicable contractual and statutory conditions. The 2026 amendments made annual release a central feature of the current system.
Current commentary describes payment as occurring after the applicable lien period, subject to outstanding liens. Dentons and Osler both identified annual holdback release as a major practical change for 2026. Project teams should therefore update older contract-administration checklists.
What Is Construction Adjudication?

Adjudication provides a faster interim process for resolving qualifying construction disputes. Ontario introduced the system as part of earlier payment reforms and expanded it further in 2026. The applicable procedures now operate with updated statutory and regulatory rules. An adjudicator’s determination is generally binding on the parties on an interim basis. A court, arbitration, or later written agreement may ultimately resolve the underlying matter differently. This makes adjudication different from a conventional final trial judgment.
The 2026 framework also broadened adjudication and introduced updated rules concerning eligible adjudicators. Ontario Regulation 264/25 now governs important parts of that system. Parties facing payment disputes should check the current statute and regulations before using older adjudication materials.
Trust Obligations Can Matter as Much as Liens
The statute contains trust provisions in addition to lien remedies. Certain project funds can be impressed with statutory trust obligations. Owners, contractors, and subcontractors may have different responsibilities depending on where money sits in the payment chain. Trust claims can become especially important when a construction business faces financial distress. They should not automatically be treated like an ordinary unsecured invoice. Insolvency proceedings can also introduce federal rules and complicated priority questions.
Lawverra’s receivership in Canada guide explains the broader creditor framework during receivership. Construction participants should still obtain project-specific advice about any asserted statutory trust.
What Owners, Contractors, and Subcontractors Should Track
Construction payment disputes often become deadline disputes. A party may have strong evidence yet lose a statutory remedy because the required step happened late. A simple project calendar can therefore prevent expensive mistakes.
Track at least these events:
- Date the contract was entered into.
- Date each invoice was delivered.
- Seven-day invoice deficiency deadline.
- Any notice of non-payment.
- Dates of each payment down the contractual chain.
- Contract anniversary dates.
- Publication of annual holdback notices.
- Date of last supply.
- Substantial performance publication.
- Completion, abandonment, or termination dates.
- Lien preservation and perfection deadlines.
- Any adjudication notices or determinations.
Keep contracts, invoices, change orders, delivery records, payment certificates, and notices together. Project correspondence can determine which statutory date applies. Informal assumptions about deadlines should never replace the current legislation.
What Happens When a Construction Dispute Reaches Court?
Some disputes continue into the Ontario Superior Court of Justice. The Act expressly provides for court enforcement of construction liens. Other contractual claims may also proceed through Ontario’s ordinary civil litigation system. Construction proceedings have features that can differ from standard civil claims. The interaction between lien rights, adjudication, contract claims, and statutory trusts can affect procedure. Parties should identify each potential legal basis before choosing their next step.
Settlement methods may also remain available in appropriate cases. Lawverra’s Ontario mediation guide explains the province’s broader civil mediation framework. That guide also notes that most Construction Act claims are excluded from Ontario’s ordinary mandatory mediation rule.
A Practical Example
Suppose a subcontractor completes work but remains unpaid. The first question is not simply whether the invoice is overdue. The subcontractor should also identify payment notices, last-supply dates, possible lien rights, and adjudication options. Assume the last supply date starts a 60-day lien clock in that particular case. Waiting several months for informal negotiations could allow the lien remedy to expire. A contractual debt claim may remain, but the available security and procedure could change substantially.
That example explains why construction payment disputes need early deadline analysis. The size of the invoice does not determine whether statutory rights matter. A relatively modest unpaid account can still carry lien, trust, or adjudication issues.
Before You Rely on a Construction Deadline
Ontario construction law contains short deadlines and fact-specific triggering events. Check the current statute, regulations, project documents, and relevant notices before acting. A date that applies to one contractor may not apply identically to another participant. Lawverra is not a law firm and does not establish a lawyer-client relationship with readers. Its full publication terms are explained in the Lawverra disclaimer.
If a lien, non-payment notice, holdback release, or adjudication deadline is approaching, consider obtaining advice from a qualified Ontario legal professional. Construction remedies can disappear before an ordinary lawsuit limitation period expires. Early review can help identify which rights remain available.
Frequently Asked Questions About the Construction Act
Does the Construction Act apply across Canada?
No, the statute discussed here is Ontario legislation. Other provinces use their own construction, builders’ lien, prompt-payment, or related statutes. Federal construction projects can also fall within the Federal Prompt Payment for Construction Work Act.
How long do I have to register a construction lien in Ontario?
Many Ontario lien claims use a 60-day preservation period. The event starting that period depends on the claimant and project circumstances. Do not calculate the deadline from the unpaid invoice date alone.
How much holdback is required in Ontario?
The basic statutory holdback is generally 10% of supplied services or materials. Separate holdback rules may apply to finishing work. Release timing also depends on the current statutory framework.
What changed on January 1, 2026?
Ontario implemented substantial amendments affecting holdbacks, proper invoices, and adjudication. Annual holdback release became mandatory under the new framework. The adjudication system and invoice-deficiency process also received important updates.
Can an owner reject an improper invoice?
An owner can raise deficiencies, but timing now matters greatly. Since 2026, written notice generally must be given within seven days after receiving the invoice. Otherwise, an invoice with deficiencies can be deemed proper for prompt-payment purposes.
Is adjudication the same as going to court?
No, statutory adjudication is designed as a faster interim dispute process. Its determination can bind the parties before final resolution elsewhere. Court proceedings or arbitration can still determine the underlying dispute in permitted circumstances.